Project Management
PMI® Case Study
COLORADO SPRINGS WELCOME HOME PARADE:
Project Management Helps Welcome the Troops Home
With a short amount of time and limited budget, the city of Colorado
Springs, Colorado, USA, planned a parade to welcome home troops
returning from Iraq. The parade was perhaps the largest in Colorado
Spring’s history, and the largest celebration of its kind in the county.
Using project management competencies found in PMI’s de facto guide
to the project management profession, A Guide to the Project
Management Body of Knowledge (PMBOK® Guide)—Third Edition, the
project team planned and executed the parade successfully in spite of
limited time and budget.
Background
Colorado Springs is home to multiple branches of the military and six
major bases, including Fort Carson and the Air Force Academy. The
town decided to plan a welcome home parade for its soldiers who had
been deployed to Iraq. Around 11,000 troops had been sent to Iraq for
year-long rotations, and were to return in March 2004.
The parade was scheduled for 5 June 2004. All floats and participants
were required to have a patriotic theme. Multiple teams came together
to plan the event.
The project management team was lead by O’Donnell & O’Donnell LLP,
which had experience with parade planning in addition to fundraising,
which would prove to be an important part of this project.
The City Council of Colorado Springs also donated city resources and
personnel to the project, including the assistant city manager, who
was the main link between the city and the project team. Providing the
team with daily access to city officials ensured key communication
throughout the project.
In addition to the project team, the city also established a
management team committee, composed of stakeholders and
representatives from each local military base. These two teams met
regularly to give status reports, offer or ask for assistance, and
determine the next steps in the project. This open forum for
communication fostered a greater understanding for each party’s role
in the project and what the end result would be. All high level changes
were made by the committee, while the detail changes were made by
the project team.
Challenges
The two major challenges of this project were the lack of money to
fund the parade and the limited timeframe to complete the project.
Security and safety also stood as risks to the event.
The project team faced the challenge of raising all funds for the
parade, as the city could not finance the event. The event budget and
reimbursement for their services would come only from the donations
and sponsorship money raised. The city capped the fee amount
O’Donnell & O’Donnell could charge them, and also established a
separate account for the event so they could accurately track finances.
Last minute changes also posed a challenge. Project stakeholders from
Fort Carson requested the troops be fed lunch after the parade. The
city raised the fee caps, but the project team had to include catering,
organization and clean-up in an already tight schedule.
Solutions
In order to combat the limited budget and timeframe, the project team
used every stakeholder’s resources, asking what each organization
could contribute to the event. The project was then approached in
reverse order; the scope of a project is typically established before the
resources, but the project team had to establish resources to
determine project scope.
Although the city could not contribute monetarily to the project, it
offered in-kind services by having every city department participate.
In addition to those workers, the project team used its own volunteer
base of 35-40 people. Many of the sponsoring organizations also
offered their services at reduced fees or free of charge. In return,
sponsors and donors received a banner and viewing stand at the
parade for their contributions.
The team used project management competencies throughout the
project to:
coordinate a donation of 40 buses from city transportation
department to transport the 6,000 soldiers participating in the
parade;
work with city police to arrange parking for buses;
coordinate with city engineers to control traffic lights to minimize
convoy’s effect on city traffic flow;
inform town in advance of any road closures or delays caused by
parade preparations; and
overcome challenge of providing last-minute lunch to troops by
securing free food and service through local restaurant franchise,
using local park as venue and volunteers from Chamber of
Commerce to help serve food.
In addition, risk management techniques were used to anticipate and
prevent potential problems:
the team held meetings with local fire and police departments
and management committees to discuss risk responses;
police responded to traffic congestion by finding alternate routes
for cars during parade;
the fire department positioned rescue crews along route in case
of an emergency; and
paramedics passed out water to prevent dehydration
Results
The parade consisted of 22 floats, 23 fire trucks and eight marching
bands, including the U.S. Army Field Band from Fort Meade, Md. Many
antique military aircraft and other vehicles took part in the parade,
and over 65,000 people came to watch the historical event and show
their support for the troops.
The public communications department for the city took care of all
publicity and interviews at no cost; three local television stations and
six local radio stations held live broadcasts from the parade and
related events; and photographers from local newspapers were on
site. The White House even issued a statement about the event, which
was read at the parade and on all local broadcasts.
Project management techniques enabled the project team to
coordinate the event, raise funds and accommodate last minute
changes within a remarkably short time frame. As a result, the
Colorado Springs Welcome Home Parade was the largest event of its
kind ever held in Colorado Springs.
Key Achievements
The project team organized and executed all aspects of the
event such as fund raising, the coordination of soldiers and
aircraft, and planning a lunch reception for 9,000 people, all
within a five month time period.
The project team executed the parade under the allocated
budget, and the city manager donated excess funds to military
charities.
Create the necessary documents to organize, plan and complete a project based on the Colorado Springs Welcome Home Parade Case
Project Charter Project __________________ Date ___________
Scope Overview
Business Case
Background (optional)
Milestone Schedule and Deliverables
Milestone
Completion Date
Stakeholder
Acceptance Criteria
Current State
Future State
Ultimate Goal
Risks and Assumptions
Project Risks and Assumptions
Risk Owner
Contingency Plans
1.
2.
3.
4.
Stakeholders
Stakeholders
Interest in Project
Primary:
Others:
Resources Required
· Funding _____________
· People ______________
· Equipment ___________
· Other _______________
Team Operating Principles
· _________________
· _________________
· _________________
Lessons Learned
· ________________
· ________________
· ________________
Commitment
Sponsor
Department / Organization
Signature
Project Manager
Department / Organization
Signature
Core Team Members
Department/ Organization
Signature